Contents
I suggest using an IT Director’s first 100 days to understand the situation and agree decision-making authority, priorities, a budget and measures of progress with the board. This is a proposed framework for a new role, not an account of my own first 100 days or a promise to complete every change within that period.

How can the board, a headhunter or a prospective line manager tell whether an IT leader is making a sound start? I see growing clarity about responsibility as a good sign: we know what needs protecting, which problems take priority, who makes the decisions and how progress will be assessed.
The experience behind this approach
As IT Director, I was responsible for systems, infrastructure, networks and security, as well as the team, budget and suppliers. I worked directly with the board.
My work included an audit, a development plan agreed with the board, budget negotiations, security policies, a helpdesk, documentation and team training.
That IT management experience informs the proposal below: what to agree at the start of a new role and how to assess progress.
Decision-making authority
The first agreement with my line manager concerns the outcomes I am accountable for and the authority I have. A broad remit such as “IT management” leaves too much room for different expectations.
I suggest recording answers to a few specific questions:
- Which decisions can I make independently, and which need board approval?
- Who resolves conflicting priorities between departments?
- Who can accept the risk of leaving a significant problem unresolved?
- Which decisions about spending, suppliers and the team fall within my authority?
- What outcomes does my line manager expect, and when will we review progress together?
The discussion should produce a short record of responsibilities, decision boundaries and escalation rules. The initial agreement should make it possible to act from the outset. Once the situation is clearer, I suggest refining it, particularly if expectations exceed the available resources.
Continuity and new initiatives
I distinguish between two areas in the proposed plan.
The first is protecting business continuity. I suggest checking which services are critical to the company, who owns them, what evidence we have that they can be restored, and where we depend on a single person or supplier. The result should identify urgent actions, accountable owners and risks that need a decision.
The second area is new initiatives: developing systems, automation, integrations or replacing existing solutions. Each proposal should identify a business problem, an owner accountable for the outcome, the expected benefit, and the money and staff time required.
In the budget, I suggest showing service operation, risk reduction and development separately. The board can then make an informed decision about what to fund, what to defer and which consequences it accepts.
If the same people are expected to maintain critical systems and deliver a new implementation, their availability needs to be agreed. Adding a project to the plan does not create extra delivery capacity.
For more on connecting business objectives with this choice of priorities, see From business goal to IT priority.
A plan for the first 100 days
The periods in the table are indicative and overlap. An urgent risk requires an immediate decision; major implementations may extend beyond this timeframe.
“Owner” means the person accountable for reaching the stated agreement or decision; they do not have to perform all the work themselves. The measures are proposals to agree once the baseline has been established.
- Authority and urgent risks1–10
- Services and team1–30
- Priorities and authority15–40
- Budget and resources30–60
- Launch and review60–100
Author’s proposal. Stages overlap; urgent risks require immediate decisions. Expand the stages below for responsibilities and measures.
Days 1–10: initial authority and urgent risks
DecisionDecision-making authority, escalation rules and priorities for urgent safeguards.
- Questions
- What am I accountable for from the outset? What could disrupt the business? What needs a decision beyond my authority?
- Owner
- Line manager or board — authority; IT Director — assessment and recommendations.
- Evidence of completion
- Recorded agreements and a list of urgent risks with owners and deadlines for decisions.
- Proposed measure
- Number of urgent risks without an owner or an agreed deadline for a decision.
Days 1–30: understanding services and the team’s work
DecisionWork required to maintain services and address the most significant gaps.
- Questions
- Which services are critical? Where do we lack cover, documentation or evidence of recovery? How are support requests handled?
- Owner
- IT Director; business process owners confirm which services are critical.
- Evidence of completion
- An agreed record of services, responsibilities and gaps; findings from available reviews and tests.
- Proposed measure
- Services with a named owner / agreed set of critical services. Separately: services with current evidence of a recovery test / services covered by the agreed test plan.
Days 15–40: priorities and confirmed scope of authority
DecisionOrder of priorities, scope of the role and initiatives deliberately deferred.
- Questions
- Which business problems are we addressing? What are we deferring? Does responsibility match authority?
- Owner
- Board — decision; IT Director — recommendation.
- Evidence of completion
- Approved priorities with reasons, outcome owners and constraints.
- Proposed measure
- Number of approved priorities without a business owner or acceptance criteria.
Days 30–60: budget and delivery capacity
DecisionFunding, allocation of people and the work that can be undertaken.
- Questions
- What resources do service operation, risk reduction and development require? Who will do the work? What are the dependencies?
- Owner
- Board or authorised decision-maker — budget; IT Director and business owners — resources.
- Evidence of completion
- Agreed budget, team availability plan and decisions about resource gaps.
- Proposed measure
- Number of initiatives authorised to start without confirmed funding or staffing.
Days 60–100: putting changes into practice and the first review
DecisionContinue, change scope, pause or escalate.
- Questions
- What is actually working? What is blocking progress? Are the assumptions still valid?
- Owner
- IT Director — review; business sponsor or board — decisions beyond the agreed authority.
- Evidence of completion
- Decision log, evidence from a sample of the processes put into operation, and acceptance of completed stages.
- Proposed measure
- Proportion of commitments accepted against agreed criteria among those due by the review date.
Each measure needs a data source, a review frequency and someone responsible for reporting. Recovery tests also need an agreed scope, success criteria and a definition of what counts as current evidence. For percentages, the denominator must be explicit: exactly what is included, and whether it has changed since the previous measurement.
A lack of reliable baseline data should be visible. Without it, a promised reduction in incidents or percentage saving cannot be justified.
Team and business agreements
Discussions with the team should produce a map of responsibilities: who maintains each service, who can provide cover, and where documentation or training is needed. If essential knowledge sits with one person, the agreement should specify what must be transferred and how we will check that cover is possible.
Discussions with the business should produce an agreed order for tackling problems. For each problem, I need a clear description of its business impact, the process owner and the condition that will show improvement.
These agreements help assess whether the leader listens and turns their findings into decisions. The number of meetings alone tells us little.
A process and a completed rollout
When assessing the first few months, I suggest being precise about the stage the work has reached.
I would consider a helpdesk operational when the agreed reporting channel works, responsibilities are assigned, prioritisation rules are defined and real requests can be traced through the process. That does not yet demonstrate better support. I would assess that using data from an agreed period and feedback from users.
Similarly, adopting a security policy confirms a decision about the rules. Evidence that people follow them is separate: for example, checks of selected cases and how exceptions are handled.
For a major implementation, the first 100 days may produce agreed requirements, a sponsor, funding, a plan and a completed preparation stage. Completing the whole implementation requires the acceptance criteria to be met, including user readiness and a handover to ongoing support. “Project started” should remain distinct from “solution accepted”.
When to involve the board
I would not wait until the audit was complete if an identified problem required a decision beyond the IT Director’s authority. In the proposed approach, this applies particularly when:
- continuity of critical business operations is at risk, and protection requires extra funding, downtime or acceptance of risk;
- the expected deadline or scope exceeds the team’s availability and budget;
- departments have conflicting priorities that cannot be resolved within the agreed authority;
- a significant problem has no business owner or requires a change to an earlier board decision.
I would present an escalation as a decision brief: what we know, what we do not yet know, the potential business impact, the options, my recommendation and when a decision is needed. I would also state the consequence of not deciding.
During an ongoing incident, I would escalate while taking protective action within my authority.
- What we know
- Impact on the business
- Available options
- Recommendation
- Decision deadline
- Cost of no decision
During an incident, escalation and protective action run in parallel. Author’s illustration, not a record of a specific incident.
Assessing the start of cooperation
The aim of the first 100 days is to give the board a coherent picture: the most significant risks are understood, priorities and funding are agreed, responsibilities are assigned and progress can be checked. For unresolved problems, we know what is blocking them and who needs to make the next decision.
For a prospective line manager, this would demonstrate that the leader can connect technical assessment with responsibility for how the business operates. For a headhunter, it provides a concrete basis for discussing the role’s scope, decisions and working relationship with the board.
About the author: Rafał Mokrowiecki has more than 20 years of IT experience, from ERP development to managing a team and budget. He served as IT Director from October 2024 to September 2025. Since October 2025, he has worked as an independent IT advisor.
Let’s discuss the scope of a permanent IT leadership role — decision-making authority, responsibility and expectations for the first few months, particularly in a manufacturing company.
This article draws on the author’s professional experience and sets out a proposed approach to starting a new role.